The following is the latest update from CenterPoint Energy:
West End
-Assessments by CNP showed the west end of the Island sustained the bulk of damage
-Crews have tomorrow’s assignments and will be out between 8:00 – 830 AM
-120 crews assigned to work on the west end
-Submerged Transmission Cable restored today
-Estimated restorations to all structures that can take power on the west end 3-4 days
East End
-15 crews assigned and working in the residential areas
-8 crews assigned and working the Port Area
-12 additional crews arrived this afternoon and will be assigned to other areas including Harborside and PI area. They are receiving their work tomorrow
CenterPoint Energy outages in Galveston County is currently at 40,000 meters
Today’s restoration was 6,000 meters
With the full force of both the 155 Mutual Assistance Crews on the Island and the MA crews on the Mainland , tomorrow’s restoration efforts should bring a larger number of restored meters