The City of Galveston will begin the next phase of its ongoing pavement preservation project in March, with more than 20 roadways scheduled for resurfacing across the island. The project is designed to repair and treat streets, helping keep roadways smooth, safe and durable for residents and visitors.
In 2023, the city completed a comprehensive pavement assessment of all municipal roadways and developed a multi-year plan to address maintenance and repairs. The first round of improvements was completed in 2024, and the upcoming phase continues the city’s efforts to maintain infrastructure across Galveston.
Residents who live on streets scheduled for repaving will receive advance notification through door hangers prior to construction beginning on their roadway.
The project is expected to continue through June with an estimated cost of approximately $1.5 million.
Contractors will apply a pavement preservation treatment known as micro-surfacing, which helps extend the life of existing roadways while improving overall driving conditions. The work will be completed in several phases, including asphalt patching, crack sealing, scrub sealing, micro-surfacing and pavement marking.
City officials noted that there will be an anticipated gap of approximately 30 days between the completion of asphalt patching and crack sealing and the start of scrub sealing, micro-surfacing and pavement marking. During that time, streets may appear unfinished, but the initial work is only part of the full resurfacing process.
Drivers may experience minor traffic delays during construction. The city encourages motorists to use caution in work zones and appreciates the public’s patience as crews work to maintain and improve roadway conditions throughout Galveston.